I’d treat municipal solar site review as a four-part pass/fail screen before design starts. The main job is to confirm solar access, roof or ground condition, electrical capacity, and permit/finance risk early, because weak site data can cost $2,000 to $5,000 per project in delays and rework.
If I had to boil the full process down, it would be this:
- Set the goal first: kWh offset, demand reduction, backup power, budget, and install type
- Screen sites at a desk: roof area, orientation, shading, drawings, panel size, zoning, and roof age
- Check the site in person: roof wear, rooftop clutter, access, shade, grading, and utility conflicts
- Review structure and electrical: added roof load, service size, breaker space, conduit path, and utility limits
- Rank sites with meter data: daytime load match, interconnection issues, roof life, and ROI risk
A few cutoff points stand out right away:
- Sites under 4.0 peak sun hours/day need closer review
- Sites under 3.5 peak sun hours/day are often poor fits for grid-tied PV
- More than 20% shading is a warning sign
- Roofs with less than 5 years of life left often need replacement first
- Panels under 100A often trigger upgrade work, while 200A+ service is a better starting point
Here’s the simple takeaway: don’t start design just because a building looks like a good solar candidate from the street. I’d move a site forward only after it clears desktop review, field checks, structural/electrical screening, and load-match review.
| Review Area | What I’d Confirm | Common Red Flag |
|---|---|---|
| Solar access | Peak sun hours, shade, orientation | Under 3.5 peak sun hours/day |
| Site condition | Roof life, roof wear, ground access | Roof near end of life |
| Electrical | Service size, breaker space, interconnection path | No backfeed room |
| Risk | Zoning, historic status, utility limits, ROI | Permit or upgrade delays |
That’s the whole article in plain English: screen hard first, then design only the sites that clear the basics.

Municipal Solar Site Review: 4-Step Feasibility Screening Process
How to Perform a Solar Site Survey
sbb-itb-034f8e1
Step 1: Desktop Screening and Document Review
Before you send anyone into the field, do the desk work first. A good desktop review can knock out weak candidates fast and save time, money, and a lot of back-and-forth. Use records you already have, plus mapping tools, to filter out poor fits before a site visit.
Check Aerial Imagery, Roof Area, Orientation, and Basic Shading
Start with satellite imagery and NREL’s PVWatts Calculator. The goal is simple: estimate usable roof area, orientation, pitch, and peak sun hours.
In most cases, south- or west-facing roofs with a 15° to 40° pitch are the strongest options. On the flip side, north-facing roofs or roofs blocked by trees, parapets, HVAC equipment, or nearby buildings should go on your watch list right away.
SEIA says shading is the single largest cause of underperforming solar systems [1]. That makes early shading review a big deal. If the shading factor is above 20%, the site may be only conditionally viable or not viable at all [1]. And if a site gets less than 3.5 peak sun hours per day, it usually doesn’t hit the minimum economic threshold for a grid-tied system unless there’s major battery storage in the mix [1].
Review Drawings, One-Lines, and Site Constraints
Once the aerial screen looks promising, move into the documents. You’re checking architectural and structural drawings, electrical one-line diagrams, and building permit history.
These records help confirm a few make-or-break details:
- Roof type and age
- Framing layout
- Main service panel rating
- Past building work that could affect solar installation
This is where weak sites often start to show cracks. A roof with less than 5 years of remaining life will usually need replacement before solar goes on [1]. Older buildings can also need structural reinforcement to meet current load requirements [4]. And don’t wait to check zoning overlays or historic district status. Those can stop a project before design even begins.
On the electrical side, look closely at panel capacity. A 200A main service panel is a good sign. Panels under 100A often need an upgrade [1]. You should also map the interconnection path from the array to the meter and review your local utility’s interconnection rules before moving ahead. Miss that step, and you can walk into avoidable delays later.
Candidate Site Comparison Table
Use a simple scoring table to rank sites before the field review. It keeps the process objective and gives finance and facilities teams a plain-English view of where attention should go next.
| Site Name | Available Area (sq ft) | Solar Access (Peak Hrs/Day) | Document Completeness | Initial Rating |
|---|---|---|---|---|
| Municipal HQ | 5,000+ | 4.5 | High (Full CAD available) | High |
| Public Works Garage | 3,500 | 4.2 | Medium (One-line diagrams only) | High |
| Historic Library | 1,200 | 3.8 | Low (Paper records) | Low |
| Community Center | 2,800 | 4.0 | High (Recent renovation) | Medium |
A site rated Low at this stage – like the Historic Library in the table – doesn’t always mean "stop." It means there’s a problem that needs a clear fix before the project moves forward. Maybe the drawings are incomplete. Maybe solar access is borderline. Either way, note what’s missing and verify it before you book a field visit.
Sites that score well can move on to field checks for roof condition, shading, and site access. The desktop screen tells your field team what to focus on.
Step 2: Field Walks and Sun Path Checks
Field walks test the assumptions that desktop screening can’t confirm. Use the site visit to check the roof, shade, and access assumptions made earlier. Satellite images and CAD drawings often miss things like roof condition, parapet height, rooftop clutter, and tight access points.
Verify Roof and Ground Conditions On Site
Start with the roof surface. Look for signs of deflection or damaged trusses. On tile roofs, lift a few representative tiles and inspect the underlayment. On metal roofs, confirm the seam type, because that determines clamp compatibility [2].
Map all rooftop equipment. It cuts into usable area and can block service access [3]. Measure parapet heights and fire setbacks at more than one point. On hip roofs, usable area can shrink fast [2].
For ground-mount or canopy sites, check grading, laydown space, and construction access. Flag subsurface utility engineering before any drilling so underground utilities can be located [6].
After you’ve mapped the physical limits, move on to measured shading.
Measure Annual Solar Access and Document Shading Risks
Use a Solar Pathfinder, clinometer, or shade app to measure year-round shading at the corners and center points of each array area [1][6]. Review the 9:00 AM to 3:00 PM window, using the winter solstice as the worst-case date [8][6]. A roof that looks clear in July can be heavily shaded in December when the sun sits lower in the sky.
Aim for at least 90% annual solar access in any array area under review [1]. If shading drops below that mark, document the exact cause. A tree that can be trimmed is one kind of issue. An adjacent building that isn’t going anywhere is another.
Even 10% shading can cut panel output by as much as 50% because shaded cells raise internal resistance [6].
Record these findings by array area so the structural and electrical teams can review them.
Field Review Risk Log Table
Log each finding by array area. This table shows which field risks need to be cleared before design.
| Array Area | Shading Risk | Roof/Ground Condition | Access Limitation | Safety/Code Flag |
|---|---|---|---|---|
| Municipal HQ – Main Roof | Low | Rooftop equipment and parapet heights to verify | Roof access needed | Fire setbacks to confirm |
| Public Works Garage – Roof | Medium | Tile or metal roof profile and underlayment to verify | Scissor lift may be required | Tree growth to monitor |
| Community Center – Parking Canopy | Low | Clearance heights and lighting pole conditions to verify | Lane closure may be needed | SUE required before foundation work |
| Public Works Garage – Ground Area | High | Grading and soil stability to confirm | Unrestricted | Underground utility path unconfirmed |
Sites with several flags in this table aren’t automatic no-go’s. But each issue needs a clear path to resolution before the project moves into structural and electrical review. A site with a confirmed underground utility conflict and high shading risk calls for a very different discussion than a site with one access issue.
Step 3: Structural Capacity and Electrical Readiness Checks
Once you’ve logged field risks in Step 2, turn those notes into go/no-go calls for structure and electrical scope. Use the Step 2 risk log to sort each site into pass, conditional, or fail before any engineering starts.
Review Roof Loads, Attachment Limits, and Structural Inputs
Start with roof load capacity. Flush-mounted rooftop PV usually adds 3 to 5 psf of dead load on pitched roofs. Ballasted systems on flat commercial roofs can add 5 to 15 psf [10][4]. That spread matters. A roof that already supports heavy HVAC units or aging insulation may not have much room left.
Pull any structural drawings you can get, then check them in the field. As-built drawings often don’t match what’s actually there [7]. Look at:
- Framing type
- Rafter or truss spacing
- Span
- Wood species
Wood species matters because it affects how much load a lag bolt can hold.
Also check whether the roof is already due for replacement under the capital plan. If it is, line up the PV schedule now. Otherwise, you risk paying for removal and reinstall later, which can cost $3 to $8 per square foot [12].
Before design begins, confirm the adopted code edition with the AHJ. In Texas coastal areas, jurisdictions often track Florida-style high-wind rules. That can mean full PE stamps and structural calculations for hurricane-zone projects [4].
Check Service Equipment, Panel Capacity, and Interconnection Path
On the electrical side, photograph every nameplate you can access: service voltage, phase, main breaker size, and panel rating [7]. Do not open panels unless a qualified electrician is present and wearing proper PPE [7].
The main figure to review is available breaker space and backfeed capacity. A 200A panel can still be a problem if there are no open breaker slots. In that case, you may need a line-side tap or a new subpanel. Line-side taps are common on commercial jobs, but they need utility coordination and usually add permit steps [7][5].
Trace the likely conduit path from the array to the interconnection point. Long runs, slab penetrations, or awkward routing can drive up cost fast and trigger invasive work later [11]. Check for transformer limits early too. That helps you avoid utility upgrade delays and the redesign cycle that tends to follow [11][3]. For rooftop systems, flag rapid-shutdown compliance at this stage as well.
Flag structural issues, AHJ constraints, and schedule risks early so budget changes don’t come as a surprise.
Structural and Electrical Review Table by Site
The ranges below are for early screening only, not final engineering values [10][11].
| Review Category | Pass (Low Risk) | Conditional (Medium Risk) | Fail (High Risk) |
|---|---|---|---|
| Structural Capacity | Modern framing; under 5 psf added load | Older rafters; needs sistering | Visible rot; structural failure |
| Electrical Headroom | 200A+ service; spare slots | 100A service; limited slots | Under 100A; no backfeed room |
| Interconnection | Existing empty conduits or chases | Long conduit runs required | Major utility or transformer upgrade |
| Roof Condition | Under 5 years old; sound material | 10–15 years old; minor repair | Over 20 years old; needs replacement |
Sites marked Conditional need a PE-stamped structural report and an MEP review before design begins. A PE-stamped structural report usually costs $300 to $650 [10]. Sites marked Fail stay on hold until the root issue is fixed or the site is removed from the candidate list. Sites that pass this screen move on to meter data review and load matching in Step 4.
Step 4: Meter Data Review, Risk Flags, and Site Ranking
Analyze Utility Bills, Interval Data, and Load Match
At this stage, rank the sites that made it through the desktop, field, and structural screens.
Pull 12 to 24 months of utility bills and interval data. Then compare each site’s daytime demand against expected PV output, usually during 9 AM to 3 PM [13]. The goal is simple: see whether the site is likely to use the solar power when it’s being produced.
Think of load match as the tie-breaker. If two sites already passed the solar, structural, and electrical checks, the one with stronger daytime use should rank higher.
Sites below 3.5 peak sun hours per day should already be out. At this point, meter data helps confirm whether the remaining sites are a good fit for daytime solar use.
Flag Early Financial, Operational, and Permitting Risks
Some risks don’t show up during a site visit. It’s smarter to flag them now, before the design scope is written.
- Weak load match: Low daytime demand
- Shading risk: Confirm against the Step 2 limit
- Interconnection limits: Check utility hosting-capacity maps
- Roof service life: Less than 5 years remaining
- Regulatory/zoning constraints: Historic or zoning review required
Conclusion: Final Feasibility Matrix to Decide What Moves Forward
Carry those flags into the final ranking table. This matrix brings together the same sites reviewed in Steps 1–3 so you can compare them side by side and decide what moves into formal design.
| Ranking Criteria | Viable | Conditionally Viable | Not Viable |
|---|---|---|---|
| Solar Access | ≥ 4.0 peak hrs/day; ≤ 20% shading [1] | 3.5–4.0 peak hrs/day; 20–35% shading [1][9] | < 3.5 peak hrs/day; > 65% shading [1][9] |
| Structural | Sound structure; roof life > 15 years [13] | Minor repairs needed; roof life 5–15 years [1] | Structural failure; roof life < 5 years [1] |
| Electrical | Adequate capacity, such as a 200A panel [1] | Requires minor panel or meter upgrade [1] | Major utility or interconnection barriers [1] |
| Economic | High ROI; low TCO; strong load match [13][6] | Marginal ROI; requires incentives to clear [1] | Negative ROI; irremediable costs [1] |
| Next Step | Proceed | Remediate | Stop |
Sites rated Viable in most categories should move ahead to formal design and permitting. Conditionally Viable sites need a clear fix before design starts. Not Viable sites should come off the active list and shift to other paths, such as community solar or off-site purchase [1].
FAQs
How do I know if a municipal site is worth a field visit?
A field visit makes sense when remote screening shows a site could work, but a few key limits still need to be checked in person.
Use the visit to confirm shading and solar access, look at the roof or ground-mount area, review the electrical setup, and catch access, zoning, or permitting issues early. That early look can help you avoid redesigns and project delays.
What issues most often delay municipal solar projects?
The most common delays usually start with bad site data or skipped early reviews. If teams miss shading issues, roof wear, undersized service panels, or electrical details that were never checked, the project often has to be revised later. And that’s where time starts slipping away.
Permitting can drag on for the same reason. If code compliance, structural integrity, zoning, wind loads, heat, or underground utilities aren’t clearly documented at the start, approvals tend to slow down. E3 Design-Build Contractor helps municipalities spot these risks before design begins.
When should a site be ruled out before design starts?
A site should be ruled out before design starts if it has constraints that make a safe or functional installation impossible.
That can include structural failure, roofs that can’t carry solar loads, shading so heavy that solar exposure falls below 3.5 peak sun hours per day, zoning or regulatory bans, protected habitats, or poor soil conditions.
E3 Design-Build Contractor helps municipalities check these feasibility factors early, so teams don’t waste time on sites that won’t work.