A $3.4M districtwide program of HVAC replacements, building automation and LED lighting.
$3,387,967
Total project value
$175,397
Annual savings
HVAC, controls and LED
Scope
2015
Completed
The Project
E3 and TASB completed a $3.4M energy-efficiency and conservation program in Hondo ISD that included LED lighting retrofit, Building Automation System Installation, and HVAC Improvements. The project is projected to save the school district approximately $175,397 annually.
Through the Design-Build delivery method, E3 worked closely with District leadership to develop and implement solutions tailored to the unique needs of each campus while maximizing long-term value from the investment. By combining mechanical, controls, and lighting improvements into a single comprehensive program, Hondo ISD was able to address deferred facility needs while achieving measurable energy savings.
The Comprehensive Project Included:
- Hondo High School: Automated Logic Building Automation System, 9 A/C unit replacements at the North Wing classrooms, 8 A/C unit replacements at the Activity Center (redesign), and LED lighting.
- McDowell Middle School: Proliphix Smartstat energy controllers and LED lighting.
- Woolls Intermediate School: Automated Logic Building Automation System, 2 outside air unit VAV conversions (redesign), and LED lighting.
- Meyer Elementary School: Proliphix Smartstat energy controllers, 31 A/C unit replacements, and LED lighting.
- Administrative support facilities: Proliphix Smartstat energy controllers and LED lighting.
Project Facts
- Funding: Contractual Obligation Financing.
- Contract type: Design-Build.
Hondo ISD Project Photos


More Client Stories

Manor ISD
A $10.2M bond-funded program of energy conservation and deferred maintenance upgrades across the district.

Mercedes ISD
A district-wide program of new HVAC, lighting, energy management and water conservation, approved unanimously by the board.

Raymondville ISD
LED lighting, HVAC upgrades, air purification, stadium lighting and a roof replacement, delivered in four phases.