Manor ISD

A $10.2M bond-funded program of energy conservation and deferred maintenance upgrades across the district.

$10,282,698

Total contract

$293,239

Annual savings

HVAC, LED and controls

Scope

Design-Build

Contract type

The Project

Facing aging infrastructure and rising utility costs, Manor ISD strategically used bond dollars, with expert budgeting assistance from E3, to launch a comprehensive, district-wide energy conservation and deferred maintenance initiative. Driven by a commitment to modernize facilities and optimize taxpayer dollars, this $10.2M project successfully combined critical mechanical upgrades with innovative efficiency measures.

Manor ISD, with budgeting assistance from E3, allocated bond dollars to implement District-wide energy conservation and deferred maintenance upgrades. Through this program, Manor ISD collaborated to:

  • Provide a stable and comfortable learning environment in MISD
  • Make needed life-cycle upgrades to existing MISD facilities
  • Implement new technologies that will benefit instruction
  • Maximize energy savings
  • Implement a long-term plan to promote efficient buildings at MISD

Project details include the following:

  • Over 200 HVAC units replaced older than 15 years, at 7 facilities
  • District-wide LED lighting retrofits- over 18,000 fixtures
  • Building automation upgrades at 14 facilities
  • Power factor correction

Timeline

In order to meet the needs of the District, much of this project was installed during the summer of 2017 in order to ensure the proper operation of MISD’s facilities for the start of school in August.

Savings

The $10.2M energy efficiency and conservation project is guaranteed to reduce operating costs by approximately $293,000, or 17%, annually for MISD. Energy efficiency rebates that were procured through Austin Energy exceeded $100,000.

More Central Texas Stories

Boyd ISD project photo

Boyd ISD

A $3.2M design-build HVAC replacement and controls program across the district’s campuses.

Bryan ISD project photo

Bryan ISD

More than $24M in phased improvements across 24 district facilities, from LED lighting to air handling replacements.

Caldwell ISD project photo

Caldwell ISD

A board-approved renovation of the HVAC and lighting systems at Caldwell High School.

Let’s Talk About Your Campus.

Every district’s buildings are different. Tell us what is happening in yours, and we will help you find the best path forward.