Client Story

Donna ISD

Two design-build programs totaling $34M: energy efficiency first, then HVAC modernization across 28 facilities.

$33,974,992

Total program value

$716,984

Annual savings, Phase I

HVAC, LED and controls

Scope

Design-Build

Contract type

The Project

E3 has delivered two design-build programs for Donna ISD: a $7.9M energy-efficiency and conservation program completed in 2019, and a $22.3M ESSER-funded HVAC modernization completed in 2025.

Phase I: Energy Efficiency and Conservation

E3 and TASB completed a $7.9M energy-efficiency and conservation program in Donna ISD that included LED lighting retrofit (20 Campuses), Building Automation System Installation (6 Campuses), and Mechanical Retrofits (9 Campuses). The 2,298,711 s.f. project was completed with zero change orders and is projected to save the school district approximately $716,984 annually and $10,754,760 during the next 15 years.

The comprehensive project included:

  • HVAC upgrades and replacements at 9 campuses, including over 80 units at Veterans Middle School
  • Building automation system installation at six campuses
  • LED lighting retrofits of over 21,000 fixtures District-wide

Phase II: Districtwide HVAC Modernization and Controls

Donna ISD selected E3 to engineer and design a districtwide ESSER-funded HVAC modernization program valued at $22.3 million. The project addresses aging mechanical infrastructure across 28 facilities, improving system reliability, indoor environmental quality, and long-term operational performance throughout the district.

The scope includes the replacement of more than 485 HVAC units, including chillers, rooftop units, split systems, and wall-pack units, along with significant upgrades to supporting mechanical equipment such as air handling units, pumps, VAV boxes, and related systems. The project also expands the district’s energy management system and implements network-based thermostats to enhance monitoring, control, and operational efficiency across all campuses.

Encompassing nearly 1.92 million square feet, the program serves two high schools, three middle schools, twelve elementary schools, an early college high school, DAEP facilities, and multiple ancillary buildings.

Project Facts

  • Phase I: $7,947,341, completed 2019, Energy Savings Performance Program.
  • Phase II: $22,333,608 contract value and $26,027,651 final construction cost including owner-directed change orders, completed 2025, ESSER funding.
  • Total program value: $33,974,992, including owner-directed change orders.

Donna ISD Project Photos

Installation and Construction Progress

Additional Project Photos

More South Texas Stories

Edcouch-Elsa ISD project photo

Edcouch-Elsa ISD

A $15.5M design-build HVAC retrofit of the North High School building.

Mercedes ISD project photo

Mercedes ISD

A district-wide program of new HVAC, lighting, energy management and water conservation, approved unanimously by the board.

Raymondville ISD project photo

Raymondville ISD

LED lighting, HVAC upgrades, air purification, stadium lighting and a roof replacement, delivered in four phases.

Let’s Talk About Your Campus.

Every district’s buildings are different. Tell us what is happening in yours, and we will help you find the best path forward.