Client Story
Ricardo ISD
A $969,814 district-wide energy program with 44 new HVAC units, projected to save about $1M over 15 years.
$969,814
Total contract
$69,000
Annual savings
HVAC, lighting and controls
Scope
Design-Build
Contract type
The Project
Entegral Solutions completed a district-wide energy efficiency and conservation program at Ricardo Independent School District. The District utilized both ARRA SECO Cool Schools Grant funds and District General Fund to pay for the $969,814 project. The project is projected to save the school district approximately $69,000 annually and $1,000,000 during the next 15 years.
The comprehensive project includes:
- Scope Overview: District-wide energy management control system, lighting and 44 new HVAC units
- Elementary School: installed 14 new, Bard wall mount units and one York rooftop unit
- Middle School: installed 18 new, Bard wall mount units
- Technology School: installed two Bard wall mount units
- Shared Facilities: The Cafeteria, Band Hall, Library, Gymnasium and Administration received 9 York roof top units
District-wide lighting upgrade included:
- Lamp Replacement: T12 to T8 lamp replacement with electronic ballasts
- System Re-lamping: Re-lamping existing with T8 25W lamps and electronic ballasts
- High Bay: High bay lighting retrofits to T8 lamps and electronic ballasts
- Fixture De-lamping: De-lamping existing fixtures – where appropriate
- Motion Sensors: Occupancy sensors – where appropriate
- Exit Signs: Installation of LED Exit signs
- CFL Retrofit: Incandescent lights were retrofitted with Compact Fluorescent bulbs
District-wide controls upgrade included:
- Network Thermostats: 63 wireless Proliphix Network Thermostats
- Remote Sensors: 5 Remote sensors for temperature averaging
Ricardo ISD Project Photos
Installation and Construction Progress






















































Completed Improvements and Retrofits
























































Additional Project Photos




















































































More South Texas Stories

Rio Hondo ISD
New chillers, air handlers, building automation and 4,480 LED fixtures, funded through ESSER and SECO.

Carrizo Springs CISD
A $15M program to renew roofs, control moisture and modernize HVAC across the district.

Donna ISD
Two design-build programs totaling $34M: energy efficiency first, then HVAC modernization across 28 facilities.