Client Story
Ferris ISD
A $15.3M phased HVAC, controls and roofing program that kept buildings in use throughout construction.
$15,281,220
Total program value
HVAC, controls and roofing
Scope
Design-Build
Contract type
The Project
Ferris Independent School District has completed substantial work across multiple campuses as part of a phased HVAC and roofing program. Completed and substantially complete work includes:
- Replacement of aging HVAC systems serving classrooms, gyms, kitchens, libraries, and support spaces
- Installation of new split-system equipment
- Roofing repairs, coatings, and full replacements
- Field inspections and coordination where roofing systems interface with existing rooftop equipment, including solar installations
- Testing, balancing, and verification to confirm systems are operating as intended
Major HVAC replacements were completed during summer months. Follow-up inspections and roofing activities have continued during the school year with minimal disruption.
How the Work Was Delivered
Ferris ISD used a design-build approach, with E3 serving as the single point of responsibility for evaluation, engineering, and construction. Rather than separating planning from execution, this model let field conditions directly inform decisions as work progressed, including on-site inspections to coordinate penetrations, verify transitions, and confirm new systems integrated properly with existing infrastructure.
Recent activity has included roof inspections adjacent to existing solar installations, confirming detailing, flashing, and interface conditions ahead of closeout. When issues were discovered in the field, they were resolved without delaying schedules or generating unnecessary change orders.
A Phased Approach That Keeps Schools Operational
Rather than tackling all facilities at once, Ferris ISD structured the work into manageable phases, with HVAC replacements first and roofing improvements, inspections, and verification following. As this phase reaches substantial completion, the district is already preparing to move into the next, using performance observations from completed work to shape future scopes.
This approach has kept buildings in use throughout construction, supported better cost control, and allowed adjustments between phases based on what was actually found in the field.
Why This Matters
Ferris ISD’s program shows how districts can modernize critical building systems without stopping instruction or relying on one-time construction efforts. Wrapping up each phase cleanly before advancing maintains accountability and keeps the program moving without carrying unresolved issues forward.
With major scopes now substantially complete, the district is shifting focus to upcoming work funded through subsequent phases, with continued emphasis on verification, coordination, and long-term performance.
HVAC Upgrades
E3 replaced over 70 HVAC units across Ferris Junior High, Lucy Mae McDonald Elementary, and Hazel Ingram Elementary, including RTUs, split systems, and heat pumps that meet or exceed 2021 IECC standards. Upgrades included needlepoint bipolar ionization for cleaner air, new outdoor air dampers, and condensate overflow protection. At McDonald Elementary, Energy Recovery Units were refurbished with new motors, VFDs, duct repairs, and ionization systems.
Building Automation System
E3 installed a new Niagara-based BAS, replacing legacy Trane/Tracer and Reliable systems to unify control across all district facilities. The BACnet-compliant system integrates RTUs, split systems, boilers, and recovery units, providing centralized programming, graphics, testing, and staff training to enhance reliability and energy management.
Roofing and Envelope
At Ingram Elementary and Ferris Junior High, E3 installed 50-mil single-ply roofing systems with new DensDeck cover boards, tapered insulation, raised curbs, and prefabricated flashings. Thermal imaging identified and repaired moisture damage before installation.
Project Facts
- Phase I: $6,050,384.
- Phase II: $9,230,836.
- Delivery: Design-Build delivered through a Professional Service Agreement and Cooperative Construction Delivery.
Watch the video case study detailing the mechanical retrofits, energy conservation measures, and utility cost-saving upgrades implemented at Ferris ISD.
Ferris ISD Project Photos
Installation and Construction Progress










































































































Additional Project Photos











More North Texas Stories

Glen Rose Medical Center
A design-build upgrade of chillers, air handlers, controls and lighting, planned to minimize disruption to patient care.

Granbury ISD
More than 200 HVAC units replaced, including 160 placed by helicopter in a single day, plus water conservation and field turf.

Greenville ISD
A turn-key program of energy management, HVAC upgrades and lighting retrofits across the district.