Client Story
Lake Worth ISD
A design-build program of 89 HVAC replacements, a new roof, LED lighting and centralized energy management.
$3,388,215
Total contract
$207,246
Annual savings
HVAC, LED and roofing
Scope
Design-Build
Contract type
The Project
Lake Worth ISD selected E3 as its design-build partner for District-wide solutions addressing aging HVAC equipment, outdated lighting systems, and non-aligned energy management systems.
A visual presentation detailing Lake Worth ISD’s districtwide energy conservation project, featuring lighting, HVAC, and building automation upgrades.
Planning and Studies
E3 developed multiple studies to analyze the appropriate track to take in addressing the aging equipment in phases that would be manageable budget wise and different approaches in doing so. Upon entering into an agreement, Lake Worth and E3 rapidly developed the optimal plan for execution over the summer months to minimize academic disruption.
Project Scope:
- 89 HVAC unit replacements across three ISD buildings
- Roof replacement
- Districtwide LED retrofit
- District wide EMS centralization and installation
Timeline
The project was approved in June of 2020 and the bulk of mechanical completed in the summer with the remainder phased in the Fall of 2020.
Savings
The savings generated as a result of the efficiency upgrades provided a comfortable re-payment schedule of the Maintenance Tax Note utilized to fund the project and allow the District to utilize Fund Balance for other District needs.
Lake Worth ISD Project Photos
Completed Improvements and Retrofits





































Additional Project Photos













More North Texas Stories

Prosper ISD
An LED upgrade at Prosper High School, won on price after a budget review for the district.

Cooke County
A full LED retrofit of more than 1,500 interior and exterior lights, saving over $21,000 a year.

Ferris ISD
A $15.3M phased HVAC, controls and roofing program that kept buildings in use throughout construction.