Client Story
Greenville ISD
A turn-key program of energy management, HVAC upgrades and lighting retrofits across the district.
$2,700,000
Total contract
$236,245
Annual savings
Controls, HVAC and lighting
Scope
Design-Build
Contract type
The Project
Greenville ISD hired E3 to undertake a district-wide energy efficiency and conservation program. This turn-key program included an energy management system installation and expansion, HVAC upgrades and lighting retrofit.
The expanded control system utilizes web connectivity, allowing facilities personnel at each district building to monitor systems from a local computer with district intranet access. DDC controls were installed at the:
- High School
- Middle School
- Vo-Ed Building
- Central Administration Office
- Wesley Martin Operations Center
- Portables and Metal Buildings across the district
As part of this project, heating, ventilation and air-conditioning upgrades were performed at several of the district facilities, including rooftop air-conditioning unit (RTU) change outs, and heat pump replacements, boiler replacements, and boiler retubing.
The district’s lighting was also modernized with the upgrade of gym lighting in five facilities from high-bay metal halide to new high-bay T8 with instant start and occupancy sensors, and the complete re-lamping of the district with 25W lamps. Occupancy sensors were installed where appropriate in order to reduce lighting hours in offices and conference rooms.
Greenville ISD Project Photos









More North Texas Stories

Lake Worth ISD
A design-build program of 89 HVAC replacements, a new roof, LED lighting and centralized energy management.

Prosper ISD
An LED upgrade at Prosper High School, won on price after a budget review for the district.

Cooke County
A full LED retrofit of more than 1,500 interior and exterior lights, saving over $21,000 a year.