A $10.3M HVAC and LED program, with equipment pre-purchased to fit a summer installation window.

$10,255,153

Total contract

HVAC and LED

Scope

BuyBoard, Design-Build

Contract and purchasing

The Project

Kennedale ISD has completed a comprehensive project with E3 and a separate ESSER-funded project. The comprehensive HVAC and LED program required rapid development and equipment pre-purchasing to fit a summer installation window.

The comprehensive project was contracted on March 26, 2024, with a total of $10,255,153. E3 purchased all equipment for the job in-house, taking on the research, sourcing and planning itself.

Project Facts

  • Scope: HVAC, LED Lighting
  • Contract amount: $10,255,153
  • Location: Kennedale, North Texas
  • Contract and purchasing: BuyBoard, Design-Build
  • Project years: 2023, with work in progress

Kennedale ISD Project Photos

More North Texas Stories

Ferris ISD project

Ferris ISD

A $15.3M phased HVAC, controls and roofing program that kept buildings in use throughout construction.

E3 energy efficiency project installation - Chiller Lift Scaled 4

Glen Rose Medical Center

A design-build upgrade of chillers, air handlers, controls and lighting, planned to minimize disruption to patient care.

Granbury ISD project photo

Granbury ISD

More than 200 HVAC units replaced, including 160 placed by helicopter in a single day, plus water conservation and field turf.